Prepare monument drawings, inscription proofs and revision records for a China factory order. Use an approval checklist before production and shipment.

Boda Stone editorial guide · Updated · Sources and scope

Before releasing a custom monument order to a factory in China, bring the drawing, stone reference, finish schedule and inscription into one approval file. Identify the revision that may be made, who can approve it and which decisions remain open. A reference photograph can explain the design; measured dimensions and written approval settle what will be produced.

Boda Stone manufactures granite monuments in Hui'an, Fujian, for overseas trade buyers. The checklist below is our editorial purchasing recommendation. Agree the actual approval contacts, inspection evidence and release conditions for your order with our team.

What the approval file must contain

Record What it establishes What to check before approval
Order and component schedule Which models, pieces and quantities are included Match each component to its drawing and quotation item
Dimensioned production drawing Sizes, profiles, interfaces, holes and decoration positions Revision, date, units, reference edges and critical features
Stone and finish references The quoted material and intended appearance Commercial name, origin information where requested, sample or current-lot reference, finish on each face
Inscription and artwork proof Wording, size, arrangement and decorative placement Names, dates, accents, punctuation, line breaks, method and any colour treatment
Approval and open-points record Who has approved what and what still prevents release Approved revision, approval date, unresolved local requirements and responsible person

A small sample cannot show every component's appearance. A rendered mockup cannot establish engraving depth or dimensional accuracy. Keep the design or photograph's source and permission information with the file; resolve unclear permission before requesting reproduction.

Make the drawing measurable

State the units on every controlling drawing. If both inches and millimetres appear, identify which dimensions govern manufacture and resolve conversion questions before approval. Do not measure a screenshot to recover a missing dimension.

Show the finished overall dimensions and each relevant component thickness. Locate holes, recesses, joints and artwork from labelled edges or centrelines. An upright monument needs an agreed die-to-base relationship; a multi-piece kerb set needs component identities, joint positions and an assembly layout. A style name cannot settle those details.

Agree which features need particular inspection and the acceptance limits for this order. See our CAD drawing support for the information needed to develop the production drawing. Where a shape follows an existing stone, use the profile measurement brief to identify the missing measurements.

Approve lettering at the intended size

Keep the wording editable during checking and approve a final-size proof with letter heights and positions. Name the lettering or etching method and any colour treatment separately. For unfamiliar fine detail, ask whether a representative result on the selected stone and finish is needed before release.

Check the smallest dates and punctuation as carefully as the family name. Reserve space for a later inscription on the drawing and retain permitted production artwork. Our lettering and font guide explains why a font name or screen preview alone may be insufficient.

Record changes before releasing the next revision

A change request should identify the affected component and old and new revisions. Ask the factory to confirm the production stage, material implications, price and schedule impact before approving the replacement file. Agree which work must wait, and confirm that superseded instructions have been withdrawn from the affected operations.

Use this blank structure for your own change record. It is an illustrative template, not a completed order or evidence that a particular release procedure has been performed.

Change-record field Information to enter
Request and identity Date, requester, order/model and component
Revision and change Old revision, proposed revision and marked location of each change
Work already completed Factory confirmation of the affected production stage
Commercial and inspection effects Material, artwork, price, timing, packing and inspection changes, or items awaiting confirmation
Approval and release Buyer approver/date, factory acknowledgement, withdrawn file and agreed release or hold status

For example, if one inscription line changes after approval, send the revised text and marked proof, identify the affected stone, and ask whether decoration has started. Confirm the consequences, approve a new revision and record the release decision. This is a purchasing example; a late change is not automatically free or still possible.

Separate manufacturing approval from local approval

The buyer or appointed local professional should obtain the requirements for the actual cemetery and plot. Pass conditions affecting manufacture, including size, component interfaces and any required fixing details, to the factory before drawing approval. Foundation design, local fixing decisions and installation need the responsible local professionals.

Use a release checklist:

  • The quotation, component schedule and drawing identify the same products and revision.
  • Dimensions, units, critical interfaces and order-specific inspection requirements are resolved.
  • Material references and face-by-face finishes are agreed.
  • The inscription and artwork proof have written approval.
  • Local conditions affecting manufacture have been provided and unresolved questions have a named owner.
  • Changes affecting price, dates or packing have written agreement.

If an essential decision is missing, agree a hold on the affected work and record what evidence will allow it to resume. Boda Stone's production timing is typically about 30 days after receipt of the 30% deposit and approval of drawings and stone or material details. Complex custom orders follow the timing confirmed in the pro forma invoice. Freight and destination handling require separate planning; a late revision needs a schedule review.

Connect the file to inspection and repeat orders

Ask for inspection photographs and measurements to identify the order, component and approved revision. Keep agreed deviation decisions with the release file. Our pre-shipment quality checks explain how to request evidence that can be compared with the specification.

Retain the drawing, component schedule, material approval, inscription files, approval messages and change log in a recoverable order archive. Add final photographs and crate marks. For a reorder, reconfirm the current stone lot and requirements; the previous approval cannot establish present availability or an identical natural-stone appearance.

Frequently asked questions

Can a photograph replace a production drawing?

A photograph can start a design discussion. Approve dimensions, profile, finishes, interfaces and artwork positions on a measured drawing before the affected work is released.

Can an inscription change after approval?

Request a revision immediately. Confirm the production stage and any cost or timing effects, then approve the replacement proof and record the release decision.

Does factory approval include cemetery permission?

Obtain cemetery permission separately. Supply its conditions affecting manufacture and check that the local permission and factory instructions describe the same design.

Sources and editorial scope

  • Cristine Bouwkamp, Superior Monument, A Case Study in Project Management, MBNews, March 2022, printed pp. 12–15, especially pp. 13–15: a historical mausoleum project case discussing written decisions and communication when requirements or contacts change.
  • Brad Myers, South Boston Memorials, So I Made a Thing … Digitizing Grid Edition, MBNews, October 2021, printed pp. 6–9: a historical workshop account of measurement references and contour alignment.
  • Heather Sturgill, AICA, Sears Monument Co., Fonts Are Important!, MBNews, April 2021, printed pp. 10–13, including discussion with Jed Hendrickson, CM, AICA: paper proofs, stone lettering and future matching.

The MBNews publisher archive is an issue-discovery route; access may require member login. These historical articles inform the general lessons. The cross-company approval checklist and blank record above are Boda Stone's editorial application, not an MBNA standard, current association approval or a verified example of our order performance.

Prepare your approval file

Send a drawing for scope review. Include models, quantities, dimensions and units, stone and finish, drawing revision and destination. Tell us whether you already import from China or are considering it, and identify the details still awaiting approval.

Download the buyer checklist